Previous Projects & Clients

Below are examples of previous projects we have completed. If you would like any further information about our previous projects and clients please contact us.

15 projects in the last 5 years nationwide. Full ground works package undertaken.

Tesco

Contract: Tesco

Contractor: Taylor Woodrow


Full ground works package, part of the Tameside building schools for the future project.

St Damien’s School

Contract: St Damien’s School

Value: £2 Million

Contractor: Carillion


Full ground works package undertaken.

Greater Manchester Police Headquarters

Contract: GMP Headquarters

Value: £500,000

Contractor: Mansell


Alterations to live tram stops at Piccadilly, Undercroft and Market Street.  Demolition of structures at the above and also Ladywell Hospital Outbuildings.  Excavation and disposal of 72,000m3 of contaminated material.  Provision and placing of 25,000 tonnes of capping in carriageway.

Manchester Metrolink Phase 2 Eccles via Salford Quays

Contract: Manchester Metrolink Phase 2

Value: £4 Million

Contractor: Laing - Ansaldo JV


Removal of 15,000m3 of Japanese Knotweed in controlled Environment.  50,000 m3 of cut to fill on former hospital site. Demolition of 5m high retaining wall for 400m alongside main Carriageway, together with ancillary buildings.  Creation of New roundabout at a live junction.  Excavation and disposal of 20,000m3 of contaminated material arising from this project.

Monsall Regeneration

Contract: Monsall Regeneration

Value: £575,000

Contractor: Edmund Nuttall Limited

 



Bulk Excavation and removal of material to facilitate dual carriageway construction and ‘box slide’ under main Manchester to Oldham line construction of ‘Finback’ bridge and feature Gateway Entrance


Manchester Business Park

Contract: Manchester Business Park

Value: £1.1 Million

Contractor: Balfour Beatty Ltd


Excavation and disposal of 30,000m3 of contaminated Material arising from this project.  Backfilling to structures With imported fill from our Mottram Quarry.  Sealing Contaminated areas with imported natural clay.  Regrading and top soiling to achieve finished levels.

Ashton Canal Corridor

Contract: Ashton Canal Corridor

Value: £750,000

Contractor: Balfour Beatty/Laing

Remediation of the former Johnson & Nephew Wireworks. Proof dig 6 metres deep for piling operations Process 300,000m3 of site won concrete in to fill material.  Disposal of 30,000m3 refuse material off-site. Import 50,000 tonnes class 1A fill.

Commonwealth Games Stadium – Enabling Works

Contract: Commonwealth Stadium

Value: £3.5 Million

Contractor: McAlpine/Park Royal

Basement excavation between contiguous piled wall with temporary props.  Bulk excavation of 20000m3 contaminated material, provision of piling mats backfilling excavations and to underside of slab with MOT Type 1 Stone

Manchester International Convention Centre

Contract: Manchester Convention Centre

Value: £350,000

Contractor: Carillion

Download Our Brochure

Get an Estimate

Our Location